Weekly Road Works Update For Greater St Francis

Kouga Local Municipality has released its latest weekly road works schedule for 27 July to 31 July 2026, with road resurfacing, pothole repairs and stormwater maintenance planned across St Francis Bay, Cape St Francis and Oyster Bay.

The programme includes asphalt overlays, slurry sealing, road pre-treatment and maintenance work aimed at improving road surfaces and preparing streets for future upgrades.

Road Refurbishment Schedule

St Francis Drive is scheduled for overlay and asphalt works, while Cockle Street will receive an asphalt overlay.

Slurry overlay work is planned for Coral Close, Limpet Close, Barnacle Way, Periwinkel Street, Abalone Avenue, Perlemoen Street and Cowrie Crescent.

Alikreukel Avenue will undergo saw cutting, cleaning and pothole patching, while Mitra Way is scheduled for pothole repairs.

Road pre-treatment work, including vegetation clearing and pothole patching, will take place on Bonnie Bend, Clove Way, Tom Brown Boulevard, Pepper Street and Nutmeg Lane.

Stormwater Maintenance

Stormwater maintenance is also scheduled for several roads during the week. The affected streets are Padrone Avenue, Cinnamon Crescent, Tom Brown Boulevard, Cayenne Drive, Pepper Street and Oyster Row.

Please Drive With Care

Residents and taxi operators are asked to drive carefully near work areas throughout the week.

Temporary road closures and road markings may be introduced where required. Residents in affected streets are encouraged to limit vehicle movements where possible to allow contractors to complete the work safely and efficiently.

Motorists can also help by reporting potholes to the Kouga Municipal Call Centre on 042 200 2200 or 081 760 9183.