There have been several queries about the exact lengths of the new groynes, as well as a few understandable questions about what will happen during the upcoming holiday season.

Herewith the details for the first three groynes

Groyne Lengths

According to the official Order of Construction map (below).

1st Groyne: 240 metres long (currently on 185 metres)

2nd Groyne: 200 metres long

3rd Groyne: 175 metres long

Holiday Season

WBHO Construction’s last working day: 10 December 2025 WBHO Construction’s first day back on site: 7 January 2026 During the holiday break, from 11 December to 6 January, the revetment road and beach access will be open to the public. The public is reminded that access is at their own risk.

Stay Informed

Further details, updates, and progress reports can be found on the St Francis Property Owners Association website under the SFPO NPC (SRA) menu. —

SFPO NPC Contact:

Lyn Aitken – Administration Manager Phone: 042 294 0594 Email: info@sfpo.co.za Office Address: 9 Philippa Place, St Francis Bay

Newsletter

Sign up for SFPO newsletters from this page

Social Media

Find us on Facebook Find us on Instagram

Further Reading:

St Francis Property Owners Association Newsletter September 2025

Work Has Begun On The Groyne At The Bottom Of Laura Road As The Official Start Of The Long Term Coastal Protection Scheme

Newsflash From St Francis Property Owners NPC (SRA) – The Spit Is Officially Closed To Members Of The Public

Dredging Pipes In Ski Canal

Verified by MonsterInsights